SWMS template · General Construction

Shopfitting Installation — Safe Work Method Statement

Safe Work Method Statement for installing retail and hospitality fit-outs, including joinery, display units, counters, shelving, bulkheads and glass, in shopping centres and occupied premises, covering centre rules, public separation, manual handling, work at height and securing units against tipping.

Category
General Construction
HRCW
1 category
Job steps
8
Hazards rated
21
PPE items
7

Shopfitting installation usually involves High Risk Construction Work because bulkheads, signage, lighting tracks and tall joinery are installed from mobile scaffolds, scissor lifts or ladders with a fall of more than 2 metres. A SWMS is required for that work. It may also involve HRCW if powered mobile plant such as forklifts operates in the loading dock or tenancy, or if you work near energised electrical services. Add those types where they apply. Removing an existing fit-out is covered by the shopfitting removal template.

Most fit-outs happen inside an operating shopping centre or next to occupied premises, so you work under the centre's rules as well as your own. Expect a centre induction, permits for hot work, out-of-hours work and smoke detector or fire system isolation, and set delivery times through the loading dock. Hoarding must keep the public out of the tenancy and stop dust and noise escaping. Night work and short programs lead to fatigue, so plan shifts and breaks.

Manual handling is the most common cause of injury. Counters, display cases, stone or solid surface tops and glass panels are heavy, awkward and often moved through public malls, lifts and service corridors on trolleys. Plan routes, use the right trolleys and lifting aids, and use two people or more for heavy items. Cutting MDF, particleboard and laminate on site creates fine wood dust, and MDF dust is a respiratory hazard. Use saws with dust extraction and wear a P2 respirator.

Tall shelving, gondolas, display units and mirrors must be fixed so they cannot tip onto staff or customers later. Follow the manufacturer's fixing details, use fixings suited to the wall or floor, and check for services before drilling into slabs and walls. Any electrical work on display lighting and power must be done by a licensed electrician, with the tenancy circuits isolated as needed.

Customise this template with the centre or building name and its induction and permit requirements, delivery and loading dock times, the hoarding arrangement, the height access equipment and who is trained to use it, the heavy items and how they will be moved, the dust controls for on-site cutting, the fixing method for tall units and glass, any fire system isolations, and the trades working in the tenancy at the same time.

High Risk Construction Work Types

  • Risk of a person falling more than 2 metres

Personal Protective Equipment

  • Steel-capped safety boots
  • Safety glasses
  • Hearing protection
  • P2 respirator (cutting MDF and board)
  • Cut-resistant gloves (glass and laminate)
  • High-visibility vest (loading dock)
  • Hard hat (where overhead work is occurring)

Risk Assessment

RatingsCatastrophicHighModerateLow

Step 1Centre induction, permits and hoarding

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Members of the public entering the work areaHighInstall full-height hoarding or barriers before work starts. Lockable access door. Keep doors closed and the area signed.LowSite Supervisor
False fire alarms or disabled fire protectionModerateRequest detector isolation from centre management before dusty or hot work, and have them restore it at the end of each shift. Hot work only under a centre hot work permit.LowSite Supervisor
Fatigue during night work and short programsModeratePlan shifts with rest breaks. Avoid long consecutive night shifts. Supervisor watches for fatigue and stops work if needed.LowSite Supervisor

Step 2Deliveries and moving joinery through the centre

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Struck by forklifts or trucks in the loading dockHighFollow the loading dock traffic rules. High-visibility vest in the dock. Stay in pedestrian zones. Unload only in the allocated bay and time.LowShopfitter
Back injury moving heavy counters, tops and cabinetsHighUse panel trolleys, furniture dollies and lifting aids. Two or more people for heavy items. Plan the route through lifts and corridors and check widths first.LowShopfitter
Trolleys striking shoppers in malls and corridorsModerateMove large items before trading hours where possible. A second person walks ahead to clear the path.LowShopfitter

Step 3Set-out and drilling into walls and slab

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Drilling into embedded cables, pipes or post-tensioned slabHighCheck drawings and ask centre management whether the slab is post-tensioned. Scan before drilling. Use the fixing depth and locations approved by the builder.LowShopfitter
Silica dust from drilling concrete and blockModerateUse drills with dust extraction. P2 respirator. Clean up with an H-class vacuum.LowShopfitter

Step 4Cutting and modifying joinery on site

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Wood dust from cutting MDF, particleboard and laminateHighUse saws and routers with dust extraction connected to an M- or H-class vacuum. P2 respirator. Cut in a set area away from other trades.LowShopfitter
Cuts and kickback from circular and track sawsHighGuards in place. Workpiece clamped or supported. Blade suited to the material. Trained users only.LowShopfitter
Noise from power toolsModerateHearing protection when cutting and drilling. Warn other trades before noisy work.LowShopfitter

Step 5Installing and securing joinery, shelving and display units

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Tall units tipping onto workers during installationHighStand tall units up with two people. Temporarily restrain them until fixed. Do not load shelves until fixings are complete.LowShopfitter
Units tipping onto staff or customers after handoverHighFix all tall shelving, gondolas, mirrors and display units to the wall or floor to the manufacturer's details, using fixings suited to the substrate. Check every fixing before handover.LowSite Supervisor
Crush injuries setting heavy stone or solid surface topsModerateUse enough people or a vacuum lifter for heavy tops. Keep fingers clear of the landing edge.LowShopfitter

Step 6Work at height on bulkheads, signage and lighting tracks

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Fall from mobile scaffold or ladderHighUse a mobile scaffold with guardrails and locked castors, or a scissor lift operated by a trained person. Ladders only for short, light work with three points of contact.LowShopfitter
Tools and materials falling onto people belowModerateExclusion zone under overhead work. Toe boards on scaffolds. Tool lanyards for work over public areas.LowShopfitter
Contact with live lighting or power circuitsHighElectrical work by a licensed electrician only. Circuits isolated and tagged before shopfitters work near them.LowElectrician

Step 7Glass and mirror installation

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Cuts from breaking glassHighCut-resistant gloves and sleeves. Carry glass vertically using suction lifters. Inspect edges for chips before lifting.LowGlazier
Glass shelves or panels falling after installationModerateUse toughened or laminated glass as specified. Install brackets and fixings to the manufacturer's details and check load ratings.LowGlazier

Step 8Final clean, waste removal and handover

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Dust exposure during clean-upModerateH-class vacuum and damp wiping. No dry sweeping or compressed air.LowShopfitter
Strain and cuts handling waste and offcutsModerateBreak down packaging as you go. Use bins and trolleys to the loading dock. Gloves for sharp offcuts.LowShopfitter

Relevant Codes of Practice

Worker Acknowledgement

By signing below, I confirm that I have read, understood and agree to comply with this Safe Work Method Statement.

NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature

Get this template

Free. Edit the Excel version, or print the PDF and fill it in by hand.