Septic Tank and Pump Well Installation — Safe Work Method Statement

Safe Work Method Statement for installing septic tanks, aerated wastewater treatment system tanks and pump wells, covering excavation of the tank pit, decommissioning the old system, lifting the tank in, anchoring against flotation, backfilling and connecting pumps and alarms.

Category
Excavation & Earthworks
HRCW
3 categories
Job steps
7
Hazards rated
20
PPE items
8

This SWMS covers installing a new precast concrete or polyethylene septic tank, aerated wastewater treatment system (AWTS) tank or sewage pump well, including replacing an old system. The tank pit is usually well over 1.5 metres deep, the tank is placed with a crane truck or excavator, and workers often get into the pit to set the bedding and make the inlet and outlet connections. That makes it High Risk Construction Work for excavation deeper than 1.5 metres and powered mobile plant, and where you are working at or near an existing tank or pump well it is also work near a confined space. A SWMS is required.

The hazards specific to this job are collapse of the pit while someone is in it levelling the base or connecting pipes; a heavy tank (a precast concrete tank can weigh several tonnes) falling or swinging during the lift; the tank floating out of the ground or cracking when groundwater is high and the tank is empty; and sewage, hydrogen sulfide and methane in existing tanks and pump wells. Nobody enters an existing tank or pump well under this SWMS. If entry is unavoidable it needs a confined space entry permit and its own SWMS. Old tanks must be pumped out by a liquid waste contractor before they are removed, filled or broken up, and open tanks left unattended are a real drowning risk, especially for children.

On-site wastewater systems generally need approval from the local council, and drainage work and connections must be done by a licensed plumber or drainer. Pumps, floats and alarms must be wired by a licensed electrician. The crane truck operator needs the high risk work licence for that crane type, and slinging out of the operator's view needs a licensed dogger. If you use an excavator to lift the tank, the machine must be rated for lifting (see the Excavator Lifting Operations template). Requirements vary between councils and states, so check with your council and your state or territory regulator.

The SWMS must address ground support for the pit, spoil and plant set-back from the edge, dewatering, how and when workers enter the pit, the lift plan for the tank, anchoring or ballasting against flotation, backfill method, and the decommissioning of any old system.

Customise this template with the tank type, size and weight, the council approval reference, the pit depth and ground support method, groundwater level, the crane or excavator used and the lift plan, the manufacturer's backfill and anchoring requirements, the liquid waste contractor for any old system, the licensed plumber and electrician, and the BYDA reference.

High Risk Construction Work Types

  • Work in or near a shaft or trench deeper than 1.5 metres, or a tunnel
  • Work in an area with movement of powered mobile plant
  • Work in or near a confined space

Personal Protective Equipment

  • Hard hat
  • High-visibility clothing
  • Steel-capped safety boots or steel-capped gumboots
  • Safety glasses
  • Waterproof nitrile gloves (long cuff) when handling sewage-contaminated material
  • Rigger's gloves for slinging
  • Hearing protection when using compactors
  • Face shield when working near pumped sewage or effluent

Risk Assessment

RatingsCatastrophicHighModerateLow

Step 1Site assessment, approvals and services location

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Striking buried power, water, gas or communications servicesCatastrophicGet BYDA plans and locate private services (house power to sheds and pumps, water lines, existing drains) with a locator. Expose services by hand or vacuum excavation within the asset owner's zone before machine digging.ModerateSupervisor
Crane truck or plant collapsing an existing tank, drain or soakage areaHighLocate the existing tank, pipes and disposal field before plant arrives. Mark them and keep heavy vehicles and outriggers off them. Set the crane up on firm ground using outrigger pads.LowSupervisor / Crane Operator
Overhead powerlines near the crane truck or excavatorCatastrophicIdentify overhead lines, including the property's service line. Plan the crane position and lift path to stay outside the approach distance set by your state's electrical safety rules, with a safety observer where needed.ModerateSupervisor / Crane Operator

Step 2Decommissioning the existing system (if replacing)

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Exposure to hydrogen sulfide and methane from the open tankHighHave the old tank pumped out by a licensed liquid waste contractor before work. Open lids from the upwind side and stand back. No entry into the tank. No smoking or ignition sources near open tanks.LowSupervisor / Liquid Waste Contractor
Infection from sewage contactModerateWear long-cuff waterproof gloves and eye protection. Wash hands before eating, drinking or smoking. Cover cuts. Hepatitis A and tetanus vaccinations recommended for workers who regularly handle sewage. Clean and disinfect tools at the end of the job.LowAll Workers
Person or child falls into an open tankCatastrophicNever leave an open tank unattended. Cover with a secured lid or plate strong enough to walk on, and fence the area. Remove, break up or fill the old tank as the council requires.LowSupervisor

Step 3Excavating the tank pit

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Pit wall collapse onto a workerCatastrophicBatter, bench or shore the pit to the excavation plan before anyone enters. Assess soil type and groundwater before digging. Inspect the pit before each entry and after rain.ModerateSupervisor / Excavator Operator
Spoil or plant surcharging the pit edgeHighKeep spoil at least 1 metre back from the edge, further in poor ground. Keep the crane truck and excavator back from the edge by the distance set in the excavation plan.LowExcavator Operator
Groundwater or rain flooding the pit and destabilising the wallsHighUse a submersible pump to keep the pit dry. Discharge water away from the pit edge. Stop and reassess the walls if seepage increases.ModerateSupervisor
Person or vehicle falls into the open pitHighFence the pit with temporary fencing whenever it is unattended, including overnight. Barricade plant approaches.LowSupervisor

Step 4Preparing the base in the pit

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Worker in the pit struck by the excavator bucketHighExcavator stops, lowers the bucket and engages the hydraulic lockout before anyone enters the pit. Material is placed only when workers are clear.LowExcavator Operator / Supervisor
Carbon monoxide from a petrol plate compactor in a deep pitHighUse an electric or diesel compactor where possible, or compact bedding from outside the pit. If a petrol compactor must be used, limit run time and monitor carbon monoxide. Stop if anyone feels dizzy or gets a headache.LowSupervisor
Fall or no way out of the pitModerateSecured ladder extending 1 metre above the pit edge, placed within the supported area.LowSupervisor

Step 5Lifting and placing the tank

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Tank falls or rigging fails during the liftCatastrophicConfirm the tank weight from the manufacturer. Prepare a lift plan with weight, radius and crane chart capacity. Lift only from the manufacturer's lifting points with rated, tagged slings and shackles. Crane operator holds the right licence class; a licensed dogger slings and directs the lift. Nobody in the pit or under the load.LowCrane Operator / Dogger / Supervisor
Tank swings and crushes a worker against the pit wall or plantHighUse tag lines to control the tank. Lower slowly into the pit. Workers enter the pit only after the tank is landed, level and stable and the slings are slack.LowDogger / Crane Operator

Step 6Anchoring, connecting pipework and backfilling

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Tank floats or cracks due to groundwater or uneven backfillHighFollow the manufacturer's backfill and anchoring instructions. Fill the tank with water progressively as backfill goes in where the manufacturer requires it. Install anchors or ballast where groundwater is high. Backfill evenly around the tank in layers.LowPlumber / Supervisor
Manual handling of lids, risers and pipeModerateUse two people or a lifting aid for heavy lids and risers. Use the excavator to place heavy pipe and materials near the pit, not hand-carry them down ladders.LowAll Workers
Connection to a live sewer or existing drain releases sewage or gasModerateLicensed plumber or drainer to make all connections. Stop upstream use of the plumbing during the connection. Wear long-cuff gloves and eye protection.LowLicensed Plumber

Step 7Electrical connection, commissioning and handover

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Electric shock from pump, float or alarm wiringHighAll wiring of pumps, floats, aerators and alarms done and tested by a licensed electrician. Isolate and lock out at the switchboard before working on any connected pump. Pump circuits protected by an RCD.LowLicensed Electrician
Person falls into the tank or pump well after handoverHighFit the manufacturer's lids and secure them with bolts or locks so they cannot be opened without tools. Check lids and risers are rated for any expected loads. Brief the owner on not opening the tank.LowPlumber / Supervisor

Relevant Codes of Practice

Worker Acknowledgement

By signing below, I confirm that I have read, understood and agree to comply with this Safe Work Method Statement.

NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature

Get this template

Free. Edit the Excel version, or print the PDF and fill it in by hand.