SWMS template · Demolition

Load-Bearing Wall Removal — Safe Work Method Statement

Safe Work Method Statement for removing or opening up a load-bearing timber or masonry wall in a house or small building, including the engineer's design, temporary propping, beam installation and load transfer.

Category
Demolition
HRCW
2 categories
Job steps
7
Hazards rated
17
PPE items
7

Removing a load-bearing wall is High Risk Construction Work on two counts: it is demolition of an element that is load-bearing, and it is a structural alteration that needs temporary support to prevent collapse. A SWMS is required, and the job must not start until an engineer's design is on site. Opening up a kitchen wall looks simple, but the wall may be carrying ceiling joists, roof loads through struts or girder trusses, an upper floor or a masonry wall above.

The engineer's design should set out the new beam size and material, the bearing length and posts at each end, how the load is carried down to footings, and the temporary propping needed while the wall is out. Where the design does not cover propping, get the engineer or a competent temporary works designer to specify it. The props, needles or strongbacks must be on both sides of the wall, sitting on a floor or ground that can take the point loads. On a suspended timber floor this usually means propping right through to the ground below, not just onto the floorboards. Building approval or a certifier inspection may be needed; check with your council or building certifier.

Hazards specific to this job are sudden collapse if props are poorly placed or kicked, overloading floors and footings, removing the top plate or lintel too early, dust from cutting brick or render, cables and pipes hidden in the wall, and handling heavy LVL or steel beams. In older homes, wall and ceiling linings may contain asbestos and paint may contain lead, so check before demolition begins.

The work needs a licensed builder in most states, and in some states a demolition licence may apply depending on the scope. Check your state or territory regulator. Electrical and plumbing services in the wall must be isolated and relocated by licensed trades. Props must stay in place until the beam and posts are fully installed and fixed, and any inspection required by the engineer or certifier is complete.

Customise this template with the engineer's drawing reference, the wall type and what it carries, the propping layout and prop ratings, the floor and footing conditions, the asbestos and lead check results, services to be relocated, the beam size and weight and how it will be lifted into place, and who signs off before props come out.

High Risk Construction Work Types

  • Demolition of an element of a structure that is load-bearing or related to its physical integrity
  • Structural alterations or repairs that require temporary support to prevent collapse

Personal Protective Equipment

  • Hard hat
  • Safety boots (steel capped)
  • Safety glasses and face shield for cutting
  • P2 respirator (fit tested) for cutting and demolition dust
  • Hearing protection
  • Heavy duty gloves
  • Long sleeves and trousers

Risk Assessment

RatingsCatastrophicHighModerateLow

Step 1Engineer's design, approvals and pre-start checks

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Wall removed without knowing what it carriesCatastrophicEngineer inspects and issues a design for the beam, posts, footings and temporary propping before work. Check the roof space and subfloor for struts, girder trusses and point loads. Drawings on site. No deviation without the engineer's written approval.LowBuilder / Engineer
Disturbing asbestos linings or lead paintHighCheck the asbestos register or have suspect linings tested before demolition. Asbestos removed under the asbestos removal SWMS first. Treat old paint as lead until tested; wet methods, no dry sanding.LowBuilder
Electric shock or flooding from services in the wallHighLicensed electrician isolates and relocates circuits in the wall. Licensed plumber caps or reroutes pipes. Confirm isolation before cutting into the wall.LowLicensed Electrician / Licensed Plumber

Step 2Setting up the work area

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Occupants or other trades entering under the propped structureHighBarricade the area on both sides of the wall. Signs at doorways. Occupants told which rooms are out of bounds. No storage or traffic around props.LowBuilder
Dust spreading through the houseModerateSeal off the work area with plastic sheeting. Cover floors. Turn off ducted air conditioning. HEPA-filtered vacuum for clean-up.LowWorkers

Step 3Installing temporary propping

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Collapse because props are undersized or poorly placedCatastrophicInstall props, needles or strongbacks exactly as the engineer or temporary works design specifies, on both sides of the wall. Use rated adjustable props within their rated load and extension. Props plumb and pinned. Supervisor checks before any demolition starts.LowBuilder / Supervisor
Floor or footings failing under prop point loadsHighSpread loads with sole plates or timber spreaders. On suspended timber floors, prop through to the ground under each prop line as designed. Check the subfloor for soft ground or rotten bearers before loading.LowBuilder
Props knocked or loosened during workHighKeep a clear zone around each prop. Check and re-tighten props at the start of each shift and after any impact. No barrows or materials moved through prop lines.LowWorkers / Supervisor

Step 4Removing linings and demolishing the wall

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Removing members in the wrong orderHighRemove linings first, then studs or masonry from the top down. Leave the top plate or lintel until the engineer's sequence allows. Stop and call the engineer if the structure is different from the drawings.LowSupervisor
Silica dust from cutting brick, block or renderHighUse saws with water suppression or on-tool extraction. Fit-tested P2 respirator as a minimum. Keep other people out of the area while cutting. Wet down debris.LowWorkers
Struck by falling bricks or debrisHighWork from a stable platform, not standing on rubble. Hard hats and face shields. Remove debris often so it does not build up against props.LowWorkers

Step 5Lifting and installing the beam and posts

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Crushing or back injury handling a heavy beamHighCheck the beam weight. Use a material lift, beam lifter or chain block for steel and long LVL beams. Team lift only for light beams. Plan the lift path through the house before starting.LowBuilder / Workers
Beam or post not bearing correctlyHighBearing length, packing, posts and fixings as per the engineer's drawing. Posts sit on footings or members confirmed by the engineer. No temporary packing left as permanent bearing.LowBuilder

Step 6Load transfer and removing props

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Props removed before the beam is fully fixed or inspectedCatastrophicProps stay until all fixings are complete and any engineer or certifier inspection is passed. Release props slowly and evenly, watching for movement or cracking. Stop and re-prop if the structure moves.LowBuilder / Engineer
Props falling when releasedModerateTwo workers to lower and remove each prop. Keep feet clear of the base.LowWorkers

Step 7Making good and clean-up

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Cuts and manual handling injuries clearing debrisModerateGloves and boots. Bag or bin debris in manageable loads. Use a barrow or chute to the skip.LowWorkers
Services restored before they are checkedModerateLicensed electrician tests and signs off relocated circuits before re-energising. Plumber pressure tests relocated pipes.LowLicensed Electrician / Licensed Plumber

Relevant Codes of Practice

Worker Acknowledgement

By signing below, I confirm that I have read, understood and agree to comply with this Safe Work Method Statement.

NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature

Get this template

Free. Edit the Excel version, or print the PDF and fill it in by hand.