Driveway and Footpath Concreting — Safe Work Method Statement

Safe Work Method Statement for residential driveways, crossovers and footpaths, covering breaking out old concrete, excavation and base preparation, formwork and mesh, concrete truck access, finishing including exposed aggregate, joint cutting and protecting the public.

Category
Concrete, Masonry & Roofing
HRCW
1 category
Job steps
7
Hazards rated
20
PPE items
8

Most driveway and footpath jobs involve High Risk Construction Work because a skid steer, mini excavator or concrete truck is moving around workers on foot. A SWMS is required. If the work includes a council crossover or a footpath in the road reserve next to traffic, it is also HRCW for work adjacent to a road in use by traffic, so add that type and a traffic management plan. Council permits for crossovers and footpath work are needed in most areas, and the requirements vary between councils.

Residential concreting is tight work. The truck often reverses up a narrow driveway past fences, cars and pits, sometimes with the owner's children or pets nearby. Use a spotter for every reverse, keep the public out with barriers, and check that the ground and any pits, tanks or stormwater pipes under the truck's path can carry the load. Pedestrians on the footpath need a safe route around the work, not just a sign.

Breaking out an old driveway is often the hardest part of the job. Jackhammers and hydraulic breakers give off noise, vibration and silica dust, and broken slabs are heavy and sharp. Underground services run under driveways and footpaths more often than people expect: water and gas services, power to the house, NBN conduit and stormwater. Get Before You Dig Australia (BYDA) plans, locate services, and take care with every excavator bucket near marked services.

Placing and finishing concrete brings cement burns, heavy reinforcing mesh, and bending and kneeling for hours. Exposed aggregate finishes involve surface retarders and washing off the surface layer, which produces alkaline wastewater that must not go down the stormwater drain. Saw cutting control joints the next day creates silica dust. Wet cut or use on-tool extraction.

Customise this template with the site address, council permit references, whether the work is on private land or in the road reserve, the BYDA reference and services located, the plant to be used, the truck access route and ground conditions, the reinforcement and finish (broom, exposed aggregate, coloured), the washout location, and how the public will be kept off the concrete while it cures.

High Risk Construction Work Types

  • Work in an area with movement of powered mobile plant

Personal Protective Equipment

  • Steel-capped safety boots (waterproof, trousers worn over boots)
  • Waterproof gloves for concrete handling
  • Cut-resistant gloves (mesh and broken concrete)
  • Safety glasses
  • Hearing protection
  • P2 respirator (breaking out and saw cutting)
  • High-visibility vest
  • Knee pads

Risk Assessment

RatingsCatastrophicHighModerateLow

Step 1Site set-up, permits and public protection

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Pedestrians walking into the work area or onto wet concreteHighBarricade the work area with fencing or barriers, not just tape. Provide a marked alternative path for footpath users as the council permit requires. Signs at both ends.LowSupervisor
Children and pets on a residential siteModerateAgree with the owner that children and pets are kept inside or away from the work during plant and truck movements.LowSupervisor
Working next to road traffic at the crossoverHighWhere work is in the road reserve next to traffic, set up traffic control to the approved plan and list this work as HRCW. Park plant and vehicles off the road where possible.ModerateSupervisor

Step 2Breaking out and removing old concrete

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Silica dust from breaking concreteHighWet the concrete while breaking. Use a hydraulic breaker on plant instead of a hand jackhammer where possible. P2 respirator for workers near the breaker.LowConcreter
Hand-arm vibration and noise from jackhammersHighHearing protection. Rotate jackhammer operators. Use low-vibration tools and limit time on the tool.ModerateConcreter
Hand and back injuries lifting broken slabsModerateBreak slabs into small pieces. Load with a skid steer or excavator. Cut-resistant gloves for exposed mesh.LowConcreter

Step 3Excavation and base preparation

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Striking gas, water, power or NBN servicesHighObtain BYDA plans. Locate and mark services. Hand dig or vacuum excavate around marked services before using the bucket nearby.LowSupervisor
Workers struck by skid steer or excavatorHighTrained operators only. Exclusion zone around operating plant. Workers on foot make eye contact with the operator before approaching. Reversing alarm working.LowPlant Operator
Dust and noise from compacting baseModerateDampen the base before compacting. Hearing protection when using a plate compactor or roller.LowConcreter

Step 4Formwork and reinforcing mesh

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Cuts and back strain handling mesh sheetsModerateTwo-person lift for full sheets. Cut-resistant gloves. Cut mesh with bolt cutters or a saw fitted with a guard and wear safety glasses.LowConcreter
Impalement or trips on starter bars, pegs and bar chairsModerateCap exposed bars and pegs. Keep pegs inside the formwork line. Walk on mesh only where needed and watch your footing.LowConcreter

Step 5Concrete truck access and placement

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Truck reversing over a worker, owner or childCatastrophicDedicated spotter for every reverse, in sight of the driver at all times. Area behind the truck kept clear. Agreed hand signals.ModerateSpotter
Truck breaking through a pit, tank, pipe or soft groundHighCheck the truck path for pits, rainwater tanks, septic systems and stormwater pipes. Use a line pump or barrows where the ground cannot take the load.LowSupervisor
Strain from barrowing and raking concreteModerateHalf-fill barrows on slopes. Use a concrete pump or extra chutes for long runs. Rotate raking and barrowing.LowConcreter

Step 6Finishing including exposed aggregate

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Cement burns to knees and handsModerateWaterproof knee pads and gloves. Wash skin contact straight away. Do not kneel in wet concrete in ordinary trousers.LowConcreter
Skin and eye contact with surface retarder and washwaterModerateRead the retarder SDS. Gloves and safety glasses when spraying and washing off. Collect washwater and keep it out of the stormwater system.LowConcreter
Slips on wet sloping surfacesModerateWork from the top of the slope down. Use boards to stand on. Non-slip boots.LowConcreter

Step 7Joint cutting, curing and clean-up

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Silica dust from cutting control jointsHighWet cut or use an on-tool extraction saw. P2 respirator. Hose or vacuum the slurry, do not dry sweep.LowConcreter
Saw kickback and blade contactHighTrained operators only. Blade guard in place, two hands on the saw, others kept clear.LowConcreter
Public or vehicles on concrete before it has curedModerateLeave barriers in place. Tell the owner how long before foot traffic and vehicles can use it.LowSupervisor

Relevant Codes of Practice

Worker Acknowledgement

By signing below, I confirm that I have read, understood and agree to comply with this Safe Work Method Statement.

NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature
NameDateSignature