SWMS template · Concrete, Masonry & Roofing
Concrete Core Drilling — Safe Work Method Statement
Safe Work Method Statement for diamond core drilling through concrete slabs, walls and soffits for service penetrations, covering scanning for reinforcement, tendons and embedded services, rig anchoring, wet drilling, core breakthrough and protection of the area below.
- Category
- Concrete, Masonry & Roofing
- HRCW
- 1 category
- Job steps
- 6
- Hazards rated
- 18
- PPE items
- 7
Core drilling is High Risk Construction Work whenever the core could pass through energised electrical cables or conduits cast into the slab or wall, which is the case on almost every existing building. A SWMS is required. It is also HRCW where you drill from a scaffold, EWP or ladder with a fall of more than 2 metres, or near a slab edge or open penetration. Add those to the SWMS where they apply. General slab sawing and wall sawing are covered by the concrete cutting template; this one is about the hazards specific to coring.
What is inside the concrete is the first problem. Slabs and walls can hold live cables, water and gas pipes, and on many commercial buildings post-tensioned tendons. Cutting a stressed tendon can release it violently and weaken the slab. Every core position should be approved by the builder or structural engineer and scanned before drilling. Ground penetrating radar is the usual method. Radiography (X-ray) needs a licensed radiography contractor and an exclusion zone, so check your state or territory radiation regulator before using it.
The second problem is what happens on the other side. When the bit breaks through, the core and water drop to the floor below or into a ceiling space, often where other trades or the public are working. Set up an exclusion zone and barricade underneath before you start, put a spotter or sign at the area below, and retain the core where possible. For wall cores, check what is on the far side.
The rig itself can hurt you. If an anchor pulls out or a vacuum base loses suction, the drill can rotate and throw the operator. Handheld drills can wrench wrists and shoulders when the bit binds. Use the anchor type and size the rig manufacturer specifies, test the anchor before drilling, and use a slip clutch on handheld drills. Wet coring keeps silica dust down, but the slurry is alkaline and slippery, and water near an electric motor needs an RCD and a water collection ring, particularly for overhead cores.
Customise this template with the core locations, diameters and depths, the engineer or builder approval reference, the scanning method and results, whether the slab is post-tensioned, the area below and how it will be barricaded, the drill type and anchoring method, how slurry and water will be collected, and the fire-rated sealing that will follow.
Important: This SWMS template is a starting point only. Review and customise it for your workplace and task. The PCBU remains responsible for ensuring the SWMS is suitable for the work. Not legal advice.
High Risk Construction Work Types
- Work on or near energised electrical installations or services
Personal Protective Equipment
- Safety glasses or face shield
- Hearing protection
- Steel-capped waterproof safety boots
- Waterproof gloves with good grip
- P2 respirator (dry coring or where slurry dries)
- Hard hat (overhead coring and work below)
- Waterproof overalls or apron
Risk Assessment
RatingsCatastrophicHighModerateLow
Step 1Core location approval and scanning
| Hazard / Risk | Initial Risk | Control Measures | Residual Risk | Responsibility |
|---|---|---|---|---|
| Cutting a post-tensioned tendon or main reinforcement | Catastrophic | Confirm whether the slab is post-tensioned from drawings or the builder. Every core location approved in writing by the builder or structural engineer. Scan with GPR and mark tendons and bars on the surface. Relocate cores that clash. | Moderate | Supervisor |
| Drilling into live cables or conduits | High | Scan each location and mark embedded services. Where services cannot be confirmed clear, have the electrician isolate the circuits before drilling. Never rely on drawings alone. | Low | Supervisor |
| Radiation exposure during X-ray scanning | High | Radiography only by a licensed radiography contractor. Clear and barricade the exclusion zone they set on all affected levels. Nobody re-enters until they give the all clear. | Low | Radiography Contractor |
Step 2Setting up the exclusion zone below and behind
| Hazard / Risk | Initial Risk | Control Measures | Residual Risk | Responsibility |
|---|---|---|---|---|
| Falling core striking a person on the floor below | High | Barricade the area below each core with a radius of at least 2 m and post signs. Check ceiling spaces for workers. A spotter or radio contact with the level below during breakthrough. | Low | Driller |
| Water and slurry damaging equipment or services below | Moderate | Cover or move equipment below. Fit a water collection ring or catch bag under overhead cores. Tell the building manager before drilling over occupied areas. | Low | Driller |
| Injury to people on the far side of a wall core | Moderate | Check the far side of the wall and barricade it. For external walls, check for public areas, windows and services outside. | Low | Driller |
Step 3Rig set-up and anchoring
| Hazard / Risk | Initial Risk | Control Measures | Residual Risk | Responsibility |
|---|---|---|---|---|
| Rig rotating or tipping if the anchor fails | High | Use the anchor size and type specified by the rig manufacturer. Drill the anchor hole clear of reinforcement, set the anchor fully and test it before coring. For vacuum bases, check the seal on a clean, flat surface and monitor the gauge throughout. | Low | Driller |
| Back strain lifting rig, motor and bits | Moderate | Carry the motor and column separately. Use a trolley on site. Two-person lift for heavy rigs and large bits. | Low | Driller |
| Electric shock from a wet electric motor | High | Drill tested and tagged and connected through an RCD (in-line RCD at the drill where supplied). Keep leads and plugs off wet floors. Use a hydraulic or air drill for heavily wet overhead work where available. | Low | Driller |
Step 4Wet core drilling
| Hazard / Risk | Initial Risk | Control Measures | Residual Risk | Responsibility |
|---|---|---|---|---|
| Wrist and shoulder injury when the bit binds | High | Rig-mount wherever possible. Handheld drills must have a working slip clutch and side handle. Do not stand in line with the handle. Ease off feed pressure when hitting steel. | Low | Driller |
| Silica dust from dry coring | High | Wet core as standard. Dry coring only with a dust extraction system fitted to the drill and a P2 respirator. Never let slurry dry and be swept. | Low | Driller |
| Noise exposure | Moderate | Hearing protection for the operator and anyone within a few metres. Warn nearby trades before starting. | Low | Driller |
Step 5Breakthrough and core removal
| Hazard / Risk | Initial Risk | Control Measures | Residual Risk | Responsibility |
|---|---|---|---|---|
| Core dropping uncontrolled through a slab | High | Confirm the area below is clear by radio or spotter just before breakthrough. Use a core retention method where possible. Slow the feed as the bit nears full depth. | Low | Driller |
| Crush and cut injuries removing cores from the bit | Moderate | Isolate the drill before freeing a stuck core. Use the correct knock-out tool, not hands. Gloves when handling cores, and large cores lifted by two people. | Low | Driller |
| Fall or trip into the open penetration | Moderate | Cover or barricade the core hole as soon as it is drilled. Covers fixed and marked until sealed by the follow-on trade. | Low | Driller |
Step 6Slurry collection and pack-up
| Hazard / Risk | Initial Risk | Control Measures | Residual Risk | Responsibility |
|---|---|---|---|---|
| Slips on wet slurry | Moderate | Wet vacuum slurry as you go. Put out wet floor signs. Clean the area before leaving. | Low | Driller |
| Skin burns from alkaline slurry | Moderate | Waterproof gloves and long sleeves. Wash skin contact straight away with clean water. | Low | Driller |
| Slurry entering stormwater drains | Moderate | Collect slurry and dispose of it as directed by the site waste plan. Do not wash it into stormwater. | Low | Driller |
Relevant Codes of Practice
Worker Acknowledgement
By signing below, I confirm that I have read, understood and agree to comply with this Safe Work Method Statement.
Get this template
Free. Edit the Excel version, or print the PDF and fill it in by hand.