Important: This SWMS template is provided as a starting point only. It must be reviewed and customised to reflect the specific conditions, hazards, and controls for your workplace and task. The PCBU remains responsible for ensuring the SWMS is suitable for the specific work. This template does not constitute legal advice. Refer to your state or territory WHS regulator for compliance requirements.
Structural & Formwork

Roof Truss Installation — Safe Work Method Statement

Safe Work Method Statement for lifting, setting, fixing and bracing prefabricated timber roof trusses on residential and light commercial buildings, including crane lifts, fall prevention at the top plate and temporary bracing to AS 4440.

Download this template

Roof truss installation is High Risk Construction Work because carpenters work at top plate height and above, with a fall of more than 2 metres both outside the building and into it. The crane lift adds powered mobile plant and possibly overhead powerlines. A SWMS is required before trusses are lifted. For housing, the Managing the Risk of Falls in Housing Construction code sets out what is expected: perimeter edge protection at eave height, and protection against falls inside the building, such as fall protection platforms or decks, or working from a scaffold or EWP.

The biggest risk specific to trusses is progressive collapse. A row of trusses that is not properly braced can domino over and take workers with it, especially in wind. Install temporary bracing as each truss is placed, following the truss manufacturer's bracing layout and AS 4440, and keep it in place until permanent bracing, battens and tie-downs are complete. Never release a truss from the crane until it is fixed at both ends and braced. Do not walk along top chords or stand on webs. Stacking roofing materials on trusses before permanent bracing is complete can overload them, so don't do it.

Crane lifts of trusses need a lift plan. Trusses are long, light and catch the wind, so tag lines, a spreader bar for long or girder trusses and a wind limit are needed. Only a licensed dogger or rigger slings and directs the lift, and nobody stands under the load. Bundles landed on the top plates must be supported and spread over walls, not dumped on a span. Overhead powerlines near the house must be identified before the crane sets up.

No WHS licence is required for carpenters setting trusses, but the crane operator and dogger need high risk work licences. The trusses must be installed in line with the manufacturer's truss layout and AS 4440, and the frame inspection required by your certifier must be completed before roofing goes on.

Customise this template with: the building height and roof form; the truss manufacturer's layout and bracing drawings; the perimeter and internal fall protection system; the crane type, set-up position and lift plan; the dogger's licence details; the overhead powerline check; the wind speed at which lifting and work on trusses stops; and the hold point for the frame inspection.

Personal Protective Equipment

Hard hatSteel-capped safety boots with slip-resistant solesSafety glassesGlovesHearing protection for nail guns and sawsHigh-visibility clothingFull body harness compliant with AS/NZS 1891 where travel restraint is the chosen controlSun protection

High Risk Construction Work Types

  • •Risk of a person falling more than 2 metres
  • •Work on or near energised electrical installations or services
  • •Work in an area with movement of powered mobile plant

Risk Assessment

1.Pre-start checks and fall protection set-up

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Falls from the top plate to the outside of the buildingCatastrophicInstall perimeter scaffold or edge protection at eave height before truss installation starts, with guardrails high enough to work for the roof pitch. Inspect it before use and after any alteration. Do not start if any section is missing or incomplete.ModerateBuilder / Site Supervisor
Falls into the building from top plates and trussesCatastrophicProvide internal fall protection before work at top plate height, such as fall protection platforms or decking at top plate level, or work from an EWP or mobile scaffold. Do not walk along top plates without fall protection. Plan the installation so carpenters work from the platform, not from the trusses.ModerateBuilder / Lead Carpenter
Crane or load contact with overhead powerlinesCatastrophicIdentify overhead powerlines and service lines before the crane sets up. Position the crane so the boom and load stay outside the network operator's exclusion zone, with a spotter where the lift works near a line. Contact the network operator if a lift cannot stay clear.LowCrane Operator / Site Supervisor

2.Lifting trusses with a crane

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Truss bundle dropped or swinging into workersCatastrophicA licensed dogger slings and directs every lift. Use a spreader bar for long and girder trusses and lift at the points the truss manufacturer specifies. Control loads with tag lines. Nobody under the load or between the load and the frame. Stop lifting when wind exceeds the limit in the lift plan.LowDogger / Crane Operator
Wall frames overloaded by landed truss bundlesHighLand bundles over load-bearing walls on the top plates, spread across several walls, never on a single span or a temporary deck not designed for it. Check that wall frames are braced and tied down before landing loads.LowLead Carpenter

3.Setting and fixing trusses

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Progressive collapse of unbraced trussesCatastrophicSet the first truss or gable end and brace it back to the ground or structure before adding more. Fix each truss at both ends with the specified connectors and tie it to the previous truss with temporary bracing as soon as it is placed. Follow the truss manufacturer's temporary bracing layout and AS 4440. Never leave trusses unbraced at the end of a shift.LowLead Carpenter
Worker falls from standing on top chords or websCatastrophicNever walk along top chords or stand on webs or bottom chords between supports. Work from the internal platform, scaffold or EWP. Where the roof form needs work above the platform, use a working platform designed for the task.ModerateCarpenter
Nail gun injuries while fixing at awkward anglesHighUse sequential-trigger nail guns for truss fixing. Never bypass safety devices. Keep the free hand well clear of the nail path. Disconnect air or remove the battery before clearing jams or moving between work areas.LowCarpenter

4.Installing permanent bracing, girders and tie-downs

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Overloading trusses before permanent bracing is completeHighDo not stack roofing, battens or other materials on trusses until permanent bracing and tie-downs are complete. Load roofing materials only as the roof installer's SWMS and the truss manufacturer allow.LowLead Carpenter / Builder
Strain from handling heavy girder trusses and bracingModeratePlace girder trusses by crane, not by hand. Two-person handling for long bracing members. Pass materials up rather than carrying them up ladders.LowCarpenter

5.Weather, inspection and handover

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Wind loading on a partially installed roof frameHighCheck the forecast before starting and stop lifting and work on trusses when wind exceeds the limit set in the SWMS. Add extra temporary bracing before leaving a partly installed frame overnight or before a forecast storm.LowLead Carpenter
Roofing started on a frame that has not been inspectedModerateComplete the frame inspection required by the certifier and fix any defects before roof cladding starts. Leave edge protection in place for the roofing trade.LowBuilder

Relevant Codes of Practice

Worker Acknowledgement

By signing below, I confirm that I have read, understood and agree to comply with this Safe Work Method Statement.

Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________