Post-Tensioning — Safe Work Method Statement
Safe Work Method Statement for installing, stressing and grouting post-tensioned slab and beam tendons, covering duct and strand placement, hydraulic stressing jacks, exclusion zones behind anchorages, tail cutting and grouting.
Download this template
Post-tensioning (PT) puts large forces into a structure. Each strand is stressed by a hydraulic jack to a very high load and locked off at the anchorage. If a strand, wedge or anchorage fails during stressing, the strand and jack components can be thrown out from the slab edge with lethal force. PT work is High Risk Construction Work because stressing crews work at slab edges and on decks with a fall of more than 2 metres, and because the work is done in an area with cranes, pumps and other powered mobile plant. A SWMS is required, and it must address the stressing exclusion zone as well as the usual deck hazards.
The key control is the exclusion zone. No one stands behind the jack, in line with the tendon, or below the anchorage during stressing, and the zone is barricaded on the deck and at the levels or ground below where an ejected strand could land. Stressing only starts once the engineer or PT designer confirms the concrete has reached the specified transfer strength, usually from test results. Hydraulic hoses, couplings and gauges must be in good condition and rated for the jack's working pressure. Gauges and jacks must be calibrated so the recorded elongations and pressures can be checked against the design.
Other PT-specific hazards include strand recoil when uncoiling strand from packs, cutting strand tails with oxy-acetylene or abrasive discs (hot work, burns), cement grout injected at pressure into ducts, and working at the slab edge from hung stressing platforms. Once tendons are stressed, the slab is a live PT structure. Any later coring, drilling or saw cutting must be scanned and approved by the engineer, because cutting a stressed tendon can release it violently and weaken the slab. Mark the slab and record tendon locations on the as-built drawings.
PT installers and stressing operators must be trained and competent with the specific system and jack. Anyone slinging crane lifts of strand packs or jacks needs a dogging licence. The PT designer's stressing sequence and records are part of the structural design and must be followed exactly.
Customise this template with: the PT system and supplier; the structural drawings and stressing sequence reference; the concrete transfer strength required and how it is confirmed; the jack and pump models and calibration dates; the exclusion zone layout at deck level and below; the stressing platform or edge access method; the tail cutting method; the grout specification; and who keeps the stressing records.
Personal Protective Equipment
High Risk Construction Work Types
- •Risk of a person falling more than 2 metres
- •Work in an area with movement of powered mobile plant
Risk Assessment
1.Delivery and handling of strand, ducts and anchorages
| Hazard / Risk | Initial Risk | Control Measures | Residual Risk | Responsibility |
|---|---|---|---|---|
| Strand recoil when opening coils | High | Uncoil strand only from a purpose-made dispenser or cage. Do not cut the strapping on a coil outside the dispenser. Stand clear of the coil when cutting straps. Wear cut-resistant gloves and a face shield when feeding strand. | Low | PT Installer |
| Load dropped during crane lifts of strand packs and jacks | High | Lifts slung and directed by a licensed dogger using rated lifting gear and the supplier's lifting points. Nobody under the load. Land packs on the deck on bearers, spread across formwork as the formwork designer allows, not stacked in one spot. | Low | Dogger / Crane Operator |
2.Placing ducts, tendons and anchorages
| Hazard / Risk | Initial Risk | Control Measures | Residual Risk | Responsibility |
|---|---|---|---|---|
| Falls at slab edges while fixing anchorages to edge forms | Catastrophic | Fix edge anchorages from inside the edge protection where possible. Where work outside the edge protection is needed, use a guarded stressing platform or an EWP. Never remove edge protection without an agreed alternative control from the principal contractor. | Moderate | PT Supervisor |
| Cuts and strain from pulling strand through ducts | Moderate | Push strand with a strand pusher where possible. Wear cut-resistant gloves. Rotate workers on long tendons. Keep walkways across tendons clear. | Low | PT Installer |
3.Pre-stressing checks
| Hazard / Risk | Initial Risk | Control Measures | Residual Risk | Responsibility |
|---|---|---|---|---|
| Stressing before the concrete has reached transfer strength | Catastrophic | Do not stress until the engineer or PT designer confirms in writing that the concrete has reached the specified transfer strength, based on test results. Check anchorage zones for honeycombing or cracking and report them before stressing. | Low | PT Supervisor / Structural Engineer |
| Hydraulic hose, coupling or gauge failure | High | Check jacks, pumps, hoses and couplings before each shift and remove damaged items. Use hoses rated for the jack's maximum working pressure. Confirm jack and gauge calibration is current. Route hoses clear of edges and plant traffic. | Low | Stressing Operator |
4.Stressing tendons
| Hazard / Risk | Initial Risk | Control Measures | Residual Risk | Responsibility |
|---|---|---|---|---|
| Struck by an ejected strand, wedge or jack component | Catastrophic | Barricade and sign an exclusion zone behind the jack and in line with the tendon, at deck level and on any level or ground area below the anchorage where a strand could land. Nobody stands behind the jack or looks along the tendon during stressing. The operator works from the side of the jack. Stop immediately if anyone enters the zone. Follow the PT designer's stressing sequence exactly. | Moderate | Stressing Operator / PT Supervisor |
| Hands caught at the jack nose or wedge plate | High | Keep hands clear of the jack nose and wedges while the jack is pressurised. Seat wedges only as the jack manufacturer describes. Release pressure fully before removing the jack. | Low | Stressing Operator |
| Falling from hung stressing platforms at the slab edge | Catastrophic | Use only stressing platforms designed for the purpose, with guardrails, and inspected before use. Do not overload them with jacks and pumps beyond their rating. Where a harness is used, connect to an anchor designed for it, not to strand or formwork. | Moderate | PT Supervisor |
5.Cutting strand tails
| Hazard / Risk | Initial Risk | Control Measures | Residual Risk | Responsibility |
|---|---|---|---|---|
| Burns and fire from oxy-acetylene or abrasive cutting | High | Cut tails only after the stressing records have been checked and approved. Prefer cutting methods that don't involve flame where the system allows. For oxy cutting, use flashback arrestors, check hoses, keep a fire extinguisher at hand and clear combustible material, and maintain a fire watch after cutting. Wear welding gloves, eye protection and flame-resistant clothing. | Low | PT Installer |
6.Grouting ducts
| Hazard / Risk | Initial Risk | Control Measures | Residual Risk | Responsibility |
|---|---|---|---|---|
| Grout spray from vents and couplings under pressure | High | Check grout hose connections are secure before pumping. Open and close vents in the order set by the grouting procedure. Never look into a vent while pumping. Relieve pressure before disconnecting. Wear goggles and chemical-resistant gloves. | Low | Grouting Operator |
| Cement dust and burns from mixing grout | Moderate | Add bagged grout to water in the mixer slowly to limit dust. Wear a P2 respirator when tipping bags. Wash grout off skin straight away and keep eyewash on hand. | Low | Grouting Operator |
7.Recording and marking the live PT slab
| Hazard / Risk | Initial Risk | Control Measures | Residual Risk | Responsibility |
|---|---|---|---|---|
| Later coring or drilling cuts a stressed tendon | Catastrophic | Hand over stressing records and as-built tendon locations to the principal contractor. Mark slabs as post-tensioned. Brief following trades that no core, drill or saw cut is made without scanning and the engineer's approval. | Low | PT Supervisor / Principal Contractor |