Important: This SWMS template is provided as a starting point only. It must be reviewed and customised to reflect the specific conditions, hazards, and controls for your workplace and task. The PCBU remains responsible for ensuring the SWMS is suitable for the specific work. This template does not constitute legal advice. Refer to your state or territory WHS regulator for compliance requirements.
General Construction

Suspended Ceiling Installation — Safe Work Method Statement

Safe Work Method Statement for installing commercial suspended grid ceilings, including set-out with lasers, fixing hangers to the slab or structure, installing grid and tiles, and working from mobile scaffold or EWP near services in the ceiling void.

Download this template

Suspended ceiling installation is often High Risk Construction Work because commercial ceilings put the installer on a mobile scaffold or EWP, and with ceilings at 3.5 metres or more, the platform can be high enough for a fall of more than 2 metres. Work in the ceiling void also means being close to live cabling, light fittings and cable trays that are energised while the building is occupied or other trades are commissioning, which is HRCW. Low ceilings installed from a podium step in an area where services are isolated may not be HRCW, but most commercial head contractors will still require a SWMS.

The biggest risk is the platform. Mobile scaffolds need to be set up on a level floor, locked, with guardrails, and never moved with people on them. Workers on scaffold should not climb onto the rails or reach up through the grid to stand on ceiling framing. EWPs (scissor lifts) bring crush risks against the slab, beams and services above, so keep watch overhead while raising.

Fixing hangers into the slab overhead is hard on the body and on the lungs. Drilling concrete above your head creates silica dust that falls into your face, so use a drill with a dust extraction attachment and wear eye protection and a P2 respirator. Powder-actuated tools are often used for hanger fixings; operators must be trained on the specific tool, and some states require a licence or certificate, so check your state or territory regulator. Repetitive overhead work causes neck and shoulder strain; plan platform heights so the work is not above head level.

Laser levels used for set-out are a minor eye hazard; do not look into the beam and use the class of laser suited to the job. Ceiling grids and tiles must be installed to AS/NZS 2785 and the manufacturer's system, and services such as fire sprinklers and detectors must not be damaged or covered.

Customise this template with the ceiling height and platform type, who confirms services in the void are isolated or protected, the slab fixing method and any powder-actuated tool details, dust extraction for drilling, the tile type and SDS, other trades working below, and how scaffolds will be moved between bays.

Personal Protective Equipment

Safety glasses (overhead drilling and fixing)P2 respirator (drilling concrete and cutting tiles)Hearing protection (drills and powder-actuated tools)Hard hatSteel-capped safety bootsGloves (grid and wire handling)

High Risk Construction Work Types

  • •Risk of a person falling more than 2 metres
  • •Work on or near energised electrical installations or services

Risk Assessment

1.Pre-start: services in the ceiling void and work area set-up

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Contact with live cabling, light fittings or cable traysCatastrophicConfirm with the electrical contractor which circuits in the void are live. Treat all cables as live unless isolated and tagged. Do not move, cut or hang off cables. Keep hanger wires clear of cable trays.LowSite Supervisor / Electrician
Workers below struck by falling itemsHighBarricade the area under the platform. Coordinate with other trades so no-one works directly below.LowSite Supervisor

2.Erecting and moving mobile scaffold or using EWP

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Fall from mobile scaffoldCatastrophicErect to the manufacturer's instructions and AS/NZS 4576 guidance with guardrails, midrails and toeboards. Lock castors. Only use on a firm level floor. Never move with anyone on it. Do not stand on rails or use ladders on the platform.LowCeiling Fixer
Crush between scissor lift and slab or servicesHighTrained operator. Look up before raising and raise slowly near the slab, beams and ductwork. Keep hands and body inside the platform rails.LowEWP Operator

3.Set-out with laser levels

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Eye damage from laser beamModerateUse the laser class suited to the task, following the manufacturer's instructions. Do not look into the beam or set it at eye height in walkways. Turn off when not in use.LowCeiling Fixer

4.Fixing hangers to the slab or structure

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Silica dust and debris falling into eyes from overhead drillingHighDrill with an extraction attachment connected to an M- or H-class vacuum. Safety glasses and P2 respirator. Do not drill directly above your face.LowCeiling Fixer
Injury from powder-actuated tool misfire or ricochetHighOnly workers trained on the specific tool use it, holding any licence required in the state. Check the slab or steel is suitable. Correct charge strength. Barricade the area behind thin material. Store cartridges securely.LowCeiling Fixer
Neck and shoulder strain from overhead workModerateSet platform height so drilling is near shoulder height. Rotate tasks and take breaks.LowCeiling Fixer

5.Installing grid and ceiling tiles

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Lacerations from cut grid and hanger wireModerateGloves when cutting and handling grid. Turn wire ends up and away. Use snips rather than grinders where practical.LowCeiling Fixer
Dust and fibre irritation from cutting mineral fibre tilesModerateCut tiles with a knife rather than a saw. Check the tile SDS. P2 respirator if cutting with power tools.LowCeiling Fixer
Damaging sprinklers or detectorsModerateCoordinate with the fire services contractor. Do not bend or knock sprinkler heads. Leave detectors uncovered.LowCeiling Fixer

6.Clean-up

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Trips on offcuts, wire and tile boxesModerateClear offcuts and packaging at the end of each bay. Keep scaffold paths clear.LowCeiling Fixer

Relevant Codes of Practice

Worker Acknowledgement

By signing below, I confirm that I have read, understood and agree to comply with this Safe Work Method Statement.

Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________