Important: This SWMS template is provided as a starting point only. It must be reviewed and customised to reflect the specific conditions, hazards, and controls for your workplace and task. The PCBU remains responsible for ensuring the SWMS is suitable for the specific work. This template does not constitute legal advice. Refer to your state or territory WHS regulator for compliance requirements.
General Construction

Plasterboard Wall and Ceiling Lining — Safe Work Method Statement

Safe Work Method Statement for hanging, fixing, setting and sanding plasterboard wall and ceiling linings in new homes, extensions and commercial fit-outs, including sheet handling, ceiling lifts, working platforms and removal of old linings.

Download this template

Wall and ceiling lining is not High Risk Construction Work by itself, but two HRCW triggers come up on most jobs. The first is a fall of more than 2 metres: lining raked or cathedral ceilings, stairwells, voids and commercial ceilings above about 3.5 metres usually means working from a mobile scaffold, trestle platform or EWP where the platform edge is high enough for a fall over 2 metres. The second is asbestos: in renovation work, the old linings, cornices and eaves being removed or cut into in homes built before 1990 may be asbestos cement sheet, and textured ceilings from that era can contain asbestos. Where neither applies, a SWMS is not legally required, but most builders and principal contractors will still ask for one.

The injuries that actually happen on lining jobs are mostly manual handling and falls from low platforms. A 13 mm sheet at 1200 x 3600 can weigh over 30 kg, and pushing sheets overhead into a ceiling by hand is a common cause of shoulder and back injury. Plan for ceiling lifts (sheet jacks), two-person carries, and deliveries placed as close as possible to the room where the sheets go. Falls from trestles, planks and stepladders at 1 to 2 metres cause serious injuries even though they are below the HRCW threshold, so platforms need to be stable, fully decked and the right height for the job.

Setting and sanding create fine dust. Jointing compounds are a respiratory irritant and some contain crystalline silica, so check the SDS. Use a sander connected to an extraction vacuum or wet-sponge finishing where you can, and wear at least a P2 respirator when dry sanding. Fixing into walls and ceilings also means drilling, screwing and cutting near existing cables and pipes, so confirm where services run and get circuits isolated by an electrician where you will be cutting into existing linings.

No specific licence is needed to hang plasterboard, but anyone operating a boom-type EWP with a boom length of 11 metres or more needs a high risk work licence, and the people erecting a scaffold from which a person or object could fall more than 4 metres need a scaffolding licence. Some states license wall and ceiling lining as a building trade for residential work, so check your state or territory regulator.

Customise this template with the building age and asbestos register or inspection result, the ceiling heights and the access equipment for each area, sheet sizes and delivery location, the extraction equipment for sanding, which circuits are isolated and by whom, and the other trades working in the same area.

Personal Protective Equipment

Safety glasses (overhead fixing and sanding)P2 respirator (sanding and cutting)Steel-capped safety bootsGloves with grip for sheet handlingHard hat (where overhead work by others or ceiling lift in use)Hearing protection (screw guns and power tools in enclosed rooms)

High Risk Construction Work Types

  • •Risk of a person falling more than 2 metres
  • •Work that involves, or is likely to involve, disturbing asbestos

Risk Assessment

1.Pre-start checks: asbestos, services and access

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Disturbing asbestos when removing or cutting into old linings, cornices or textured ceilingsCatastrophicFor buildings built before 1990, check the asbestos register or get the material inspected and tested before any removal or cutting. Do not cut, break or sand suspected asbestos sheet. Non-friable removal of more than 10 m2 must be done by a licensed removalist; any removal is done to the asbestos removal code, not by the lining crew as general strip-out.LowBuilder / Site Supervisor
Contact with live cables when cutting or fixing into existing walls and ceilingsHighAsk the electrician to identify and isolate circuits in the work area before existing linings are cut or removed. Use a cable detector before drilling or cutting. Cut openings with a hand saw or shallow-set oscillating tool, not a deep plunge cut. Treat all cables as live until confirmed isolated and tagged.LowElectrician / Plasterer

2.Delivery, storage and carrying of plasterboard sheets

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Back and shoulder injury carrying full-size sheetsHighArrange delivery with a crane truck or loader direct to each floor or room where possible. Use sheet trolleys or carts on level floors. Two people carry sheets longer than 2.4 m or heavier than about 20 kg. Do not carry sheets up stairs alone. Rotate tasks across the day.ModeratePlasterer / Leading Hand
Stacked sheets falling or floor overloadedModerateStack sheets flat on level bearers, not leaning against walls or frames. Keep stacks clear of doorways and access paths. Confirm with the builder that upper floors and suspended slabs can take the stack weight before loading.LowPlasterer / Builder

3.Setting up working platforms and access equipment

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Fall from trestles, planks or stepladdersHighUse plasterers trestles or a mobile scaffold with a fully decked platform at least 450 mm wide. Planks overlap and secured, no gaps. Platform at a height that lets you work without overreaching. Stepladders only for short tasks with three points of contact; never stand on the top two steps.LowPlasterer
Fall of more than 2 m in stairwells, voids or high ceilingsCatastrophicUse a mobile scaffold with guardrails, midrails and toeboards, wheels locked, erected to the manufacturer's instructions and AS/NZS 4576 guidance, or an EWP operated by a trained (and where required licensed) operator. Install edge protection or cover stairwell voids before lining begins. Do not bridge planks over stairwells.LowSite Supervisor / Scaffolder

4.Hanging and fixing ceiling sheets

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Musculoskeletal injury pushing sheets overhead by handHighUse a ceiling lift (sheet jack) for all ceiling sheets. Lock the lift wheels and winch once at height. Never stand under a sheet held only by a lift. Where a lift cannot be used, two people with props or a dead man support the sheet while it is fixed.ModeratePlasterer
Eye injury from debris and dust falling during overhead fixingModerateWear safety glasses when fixing overhead. Clear the ceiling framing of offcuts before lifting sheets. Keep screws in a pouch, not loose on the platform.LowPlasterer

5.Cutting and fixing wall sheets

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Lacerations from utility knives and sawsModerateUse retractable knives and replace blades often. Cut away from the body on a stable surface. Use a jab saw or router with a guide for service openings. Keep hands clear of the cut line.LowPlasterer
Sheets falling while being positioned on wallsModerateUse a sheet lifter (foot lever) to raise and hold sheets. Do not leave sheets leaning unfixed against frames. Fix top sheets first with a second worker holding.LowPlasterer

6.Setting, cornice installation and sanding

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Inhalation of fine dust when sanding jointsHighUse a pole or orbital sander connected to a vacuum with an M- or H-class filter, or wet-sponge finish. P2 respirator minimum during dry sanding. Close off the room from other trades and keep doors shut. Clean with a vacuum, never dry sweep or blow down with compressed air.LowPlasterer
Skin irritation from setting compounds and cornice cementModerateRead the SDS for each compound. Mix powders with low dust pouring, in a ventilated area. Wear gloves and wash skin promptly after contact.LowPlasterer

7.Clean-up and waste removal

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Slips and trips on offcuts and wet compoundModerateClear offcuts to a skip or waste bag at the end of each room. Keep stairs and access paths clear at all times. Clean up wet compound spills immediately.LowPlasterer

Relevant Codes of Practice

Worker Acknowledgement

By signing below, I confirm that I have read, understood and agree to comply with this Safe Work Method Statement.

Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________

Download this template

Go paperless with WorkSignals

Manage SWMS digitally — track sign-offs, attach photos, and access everything from your phone.

Try WorkSignals free