Important: This SWMS template is provided as a starting point only. It must be reviewed and customised to reflect the specific conditions, hazards, and controls for your workplace and task. The PCBU remains responsible for ensuring the SWMS is suitable for the specific work. This template does not constitute legal advice. Refer to your state or territory WHS regulator for compliance requirements.
Electrical Work

Lighting Installation — Safe Work Method Statement

Safe Work Method Statement for installing and replacing light fittings, downlights, LED battens, high-bay lights and exterior lighting in residential, commercial and warehouse buildings, including work in ceiling spaces and from ladders, scaffolds and EWPs.

Download this template

Lighting installation becomes high risk construction work when there is a risk of a person falling more than 2 metres or when the work is on or near energised electrical installations, so most commercial and warehouse lighting jobs need a SWMS. A residential downlight swap from a 1.5 metre platform ladder with the circuit isolated may not trigger the requirement, but principal contractors usually ask for one anyway.

The hazards that hurt electricians on lighting jobs are falls from ladders, falls through ceilings while working in roof spaces, and shocks from lighting circuits that were thought to be dead. Lighting circuits are a known trap: switch wires, shared neutrals, two-way switching and circuits fed from more than one board mean a light can still be live after the switch or one breaker is turned off. Older buildings add asbestos in ceilings, eaves and switchboard backing boards, and in the ACT and parts of NSW, homes affected by loose-fill asbestos insulation. Roof spaces in summer can reach temperatures that cause heat illness within an hour. Recessed lights also need the clearances to insulation and building materials required by AS/NZS 3000 and the manufacturer, or they become a fire risk.

The work must be carried out by a licensed electrician holding the licence required in your state or territory and comply with AS/NZS 3000. Boom-type EWPs with a boom length of 11 metres or more need a high risk work licence; operators of scissor lifts and smaller booms still need training and familiarisation on the unit.

Your SWMS must cover the access method for each height, how circuits are isolated and proven dead, what to do before entering a ceiling space, and how fittings are handled overhead.

Customise this template with the building type and ceiling heights, the number and type of fittings, the access equipment (platform ladder, mobile scaffold, scissor lift or boom), the circuits and boards to be isolated, the asbestos register details for the building, and how insulation clearances will be achieved.

Personal Protective Equipment

Safety glassesNon-conductive safety bootsHard hat (commercial sites and EWP work)Full body harness and short lanyard (boom-type EWP)P2 disposable respirator (ceiling spaces)Long sleeves and gloves for ceiling space insulation

High Risk Construction Work Types

  • •Risk of a person falling more than 2 metres
  • •Work on or near energised electrical installations or services

Risk Assessment

1.Plan access and set up the work area

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Falls from step ladders during repetitive overhead workHighChoose the access method by height and quantity: platform ladder with handrails for low ceilings, mobile scaffold or scissor lift for long runs and ceilings above about 3.5 metres, boom lift where floor access is limited. Do not stand on the top two steps of a step ladder or use an A-frame against a wall. Inspect ladders before use and remove damaged ones from service.LowLicensed Electrician / Supervisor
EWP tip-over or crush against roof structureHighCheck the floor can carry the EWP and is clear of pits, penetrations and slopes. Complete the pre-start check. Operators of boom-type EWPs with a boom of 11 metres or more must hold the high risk work licence. Watch overhead for purlins, sprinkler pipes and cable trays when elevating, and have a ground person trained to lower the platform in an emergency.LowEWP Operator / Supervisor
Falling tools or fittings striking people belowModerateBarricade the area under the work position. Use tool lanyards on EWPs and carry fittings up in a bag or box rather than in hand.LowLicensed Electrician

2.Isolate and prove lighting circuits dead

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Shock from a light fitting fed by a switch wire, shared neutral or second boardCatastrophicIsolate the circuit at the circuit breaker, not the light switch. Lock and tag the breaker. Test for dead at the fitting between all conductors including active, switch wire, neutral and earth, using a proven tester. Where two-way switching, multiple boards or shared neutrals may exist, test every conductor in the fitting before touching it. Do not rely on a non-contact tester alone.LowLicensed Electrician
Circuit re-energised by someone else while work is in progressHighFit personal lock and danger tag at the board. In occupied buildings tell the building manager which areas will be without lighting and provide temporary lighting so the isolation is not undone to restore light.LowLicensed Electrician

3.Ceiling space entry and cable work

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Falling through plasterboard ceilingHighOnly move on ceiling joists or on crawl boards spanning at least three joists. Use a torch or lead light to see joists before each move. Do not step between joists on plasterboard.LowLicensed Electrician
Exposure to asbestos in ceiling materials or loose-fill insulationHighCheck the asbestos register for commercial buildings. For homes, ask the owner about the age of the home and check whether the property is on a loose-fill asbestos register where one exists. Do not enter or disturb suspected asbestos material; stop and arrange testing. Wear a P2 respirator for general ceiling dust.LowLicensed Electrician / Supervisor
Heat stress in roof spacesHighSchedule roof space work for the morning in hot weather. Limit time in the roof space to short periods with breaks out of the heat, carry water, and have a second person check in at least every 20 minutes.ModerateLicensed Electrician / Supervisor

4.Installing and connecting fittings

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Neck and shoulder strain from prolonged overhead workModeratePosition the platform so work is at chest to head height rather than at full reach. Pre-terminate fittings at ground level where possible. Rotate tasks on large jobs.LowLicensed Electrician
Heavy high-bay or batten fittings falling during fixingHighFix brackets and hooks before lifting the fitting. Use the fixings the manufacturer specifies for the structure and fit safety chains or wires where provided. Two people for fittings over 15 kg or awkward lengths.LowLicensed Electrician
Fire from recessed lights in contact with insulation or timberHighInstall recessed fittings with the clearances to insulation and combustible material required by AS/NZS 3000 and the manufacturer, or use fittings rated for covering by insulation. Fit barriers where required. Check transformers and drivers are not buried in insulation.LowLicensed Electrician

5.Testing, re-energising and clean-up

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Wiring faults causing shock when re-energisedHighBefore removing locks, complete insulation resistance, earth continuity and polarity tests on modified circuits. Make sure all fittings are closed up and no one is in the ceiling space. Record results on the certificate required in your state.LowLicensed Electrician
Old fluorescent tubes and lamps broken during disposalModerateKeep removed fluorescent tubes and HID lamps whole in their boxes and send them to lamp recycling. Clean up broken lamps with gloves and a damp cloth, not a broom.LowLicensed Electrician

Relevant Codes of Practice

Worker Acknowledgement

By signing below, I confirm that I have read, understood and agree to comply with this Safe Work Method Statement.

Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________

Download this template

Go paperless with WorkSignals

Manage SWMS digitally — track sign-offs, attach photos, and access everything from your phone.

Try WorkSignals free