Important: This SWMS template is provided as a starting point only. It must be reviewed and customised to reflect the specific conditions, hazards, and controls for your workplace and task. The PCBU remains responsible for ensuring the SWMS is suitable for the specific work. This template does not constitute legal advice. Refer to your state or territory WHS regulator for compliance requirements.
Demolition

Hydrodemolition — Safe Work Method Statement

Safe Work Method Statement for removing concrete with ultra-high-pressure water using a remote-controlled hydrodemolition robot or handheld lance, covering set-up, structural checks, operation, slurry management and clean-up.

Download this template

Hydrodemolition removes deteriorated or sound concrete with water jets at pressures that can exceed 1000 bar, leaving reinforcement intact for concrete repair on bridges, car parks, wharves and slabs. The water jet will cut through skin, muscle and bone, and injection injuries can be fatal hours later. Hydrodemolition is High Risk Construction Work where it removes concrete that forms part of the load path, because removing cover and concrete around reinforcement can affect the structure's integrity and may require temporary propping. Powered mobile plant (the robot and the power pack truck) is also moving, and work on car park decks, bridges or wharves often involves a fall risk of more than 2 metres.

Robot operation is preferred over handheld lancing. The operator stays outside the jet's range with the remote, and the work area is fully enclosed. Handheld lancing at these pressures carries a much higher risk and should be limited to small areas the robot cannot reach. AS/NZS 4233.1 sets requirements for the safe operation of high-pressure water jetting systems, including hydrodemolition, and operators must be trained and competent to it.

Other task-specific hazards include flying concrete and steel fragments that can travel well beyond the immediate work area, noise often well over 100 dB(A), high-pH slurry that burns skin and is a pollutant, embedded electrical conduits and post-tensioning tendons, and water getting into floors below. Before starting, an engineer should define the removal depth and area and confirm whether propping is needed.

Slurry from hydrodemolition is highly alkaline and contains fine concrete particles. It must be collected, settled and pH-adjusted before any discharge, and discharge to sewer or stormwater usually needs approval from the water authority or local council.

Customise this template with the structure and elements being treated, the engineer's removal specification and propping design, the pump pressure and flow, the robot and lance equipment, the exclusion zone and screening layout, embedded services and tendons located, the slurry treatment and discharge approval, and the noise management plan.

Personal Protective Equipment

Hard hat with face shieldSafety glasses or gogglesWaterproof jacket and trousersLance operator protective clothing and boots rated for water jetting (handheld lancing)Waterproof steel-capped bootsHearing protection (earplugs and earmuffs together)Chemical-resistant gloves (alkaline slurry)High-visibility clothing

High Risk Construction Work Types

  • •Risk of a person falling more than 2 metres
  • •Demolition of an element of a structure that is load-bearing or related to its physical integrity
  • •Structural alterations or repairs that require temporary support to prevent collapse
  • •Work in an area with movement of powered mobile plant

Risk Assessment

1.Engineering review and service location

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Removal weakens the structureCatastrophicEngineer specifies removal depth, area and sequence and any propping. Props installed and checked before removal starts. Removal stops if unexpected cracking, deflection or exposed tendons are found.LowEngineer / Supervisor
Jet cuts live conduits or post-tensioning tendonsCatastrophicScan the slab to locate conduits and tendons. Isolate embedded electrical circuits. Mark no-go areas and set robot limits around them.LowSupervisor / Licensed Electrician

2.Set-up of pump unit, hoses and work area

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Hose or fitting failure under ultra-high pressureHighUse hoses and fittings rated above pump maximum pressure. Inspect daily and replace damaged hoses. Whip checks on all connections. Hose runs protected from plant and kept out of walkways.LowPump Operator
Flying debris leaves the work areaHighEnclose the work area with screens or barriers that contain rebound. Exclusion zone sized for the pressure and set-up and marked with signage. Protect openings, edges and soffits below.LowSupervisor
Fall from edge of deck or bridgeCatastrophicEdge protection in place at all open edges and penetrations before work starts.LowSupervisor

3.Robot hydrodemolition

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Jet strikes a personCatastrophicOperator stays outside the robot's reach and jet trajectory. Nobody enters the exclusion zone while the jet is on. Pump and robot have emergency stops; the remote has a dead-man function tested at start-up.LowRobot Operator
Robot tips or falls through weakened deckHighEngineer confirms deck can carry the robot. Robot kept on sound concrete away from edges and openings.LowRobot Operator / Engineer
Noise-induced hearing lossHighDouble hearing protection for crew inside the zone. Pump unit placed away from occupied areas. Comply with permitted work hours.LowAll Workers

4.Handheld lancing in areas the robot cannot reach

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Water jet injection injury to lance operatorCatastrophicHandheld lancing only by operators trained to AS/NZS 4233.1. Lance fitted with dead-man trigger and correct length. Two-person team with the pump operator in line of sight. Pressure set to the lowest effective level. Any jet injury treated as a medical emergency; operator carries a medical alert card describing water injection injury.ModerateLance Operator / Pump Operator
Fatigue and loss of control from jet reaction forceHighLimit lancing time and rotate operators. Use a shoulder stock or lance support where available.ModerateSupervisor

5.Slurry and water management

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Alkaline slurry burns to skin and eyesModerateWaterproof clothing and chemical gloves. Eye wash on site. Wash skin contact immediately.LowAll Workers
Slurry enters stormwater or leaks to areas belowHighSeal drains. Collect slurry with vacuum truck or bunded sump. Settle and adjust pH before discharge under the approval. Protect floors and vehicles below from water leaking through the slab.LowSupervisor

6.Clean-up and handover

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Slips and trips on wet, broken surfaces with exposed reinforcementModerateVacuum loose material. Mark or cover exposed bars. Restrict access until the area is ready for repair works.LowCrew
Stored pressure when disconnecting equipmentHighShut down pump and bleed pressure to zero before disconnecting hoses or lance.LowPump Operator

Relevant Codes of Practice

Worker Acknowledgement

By signing below, I confirm that I have read, understood and agree to comply with this Safe Work Method Statement.

Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________