Important: This SWMS template is provided as a starting point only. It must be reviewed and customised to reflect the specific conditions, hazards, and controls for your workplace and task. The PCBU remains responsible for ensuring the SWMS is suitable for the specific work. This template does not constitute legal advice. Refer to your state or territory WHS regulator for compliance requirements.
Demolition

Chimney Removal — Safe Work Method Statement

Safe Work Method Statement for demolishing a brick chimney stack above a roof and removing the internal chimney breast, including roof access, top-down hand demolition, debris control and making good the roof.

Download this template

Chimney removal is a small job with big consequences. The work happens at height on a pitched roof, the stack is often old and loosely bonded, and a single dropped brick can kill someone below. Removing a chimney is High Risk Construction Work because there is a risk of falling more than 2 metres, and because the stack and breast are part of the structure: removing the breast while leaving the stack, or removing part of a chimney that supports joists or a wall, requires temporary support to prevent collapse. Older chimneys may also have asbestos cement flue pipes, flashings or backing boards. A SWMS is required.

The stack must come down from the top by hand, a course or two at a time, never by pulling or pushing it over. Bricks and rubble go down a debris chute into a skip or are lowered in buckets; they are never thrown or dropped down the flue, which can blow out the fireplace or overload a hearth. Soot contains polycyclic aromatic hydrocarbons and is a known cancer hazard, so flues should be swept or sealed and dust controlled. Lead flashings must be handled with gloves and good hygiene.

Where the internal breast is being removed, get an engineer or competent person to confirm how any remaining stack, roof framing or floor joists are supported. A partial removal that leaves the stack in the roof space hanging off nothing is a well-known cause of collapse.

Edge protection or scaffolding is the expected control for roof work. Scaffolding where a person or object could fall more than 4 metres must be erected by a licensed scaffolder. Work from a harness on its own is a lower-order control and must be justified.

Customise this template with the chimney height above the roof, the roof pitch and material, the access and fall protection method, whether the internal breast is being removed and the support design, any asbestos register findings, the debris chute and skip location, and how the roof penetration will be weatherproofed.

Personal Protective Equipment

Hard hat with chin strapSafety glassesP2 respiratorDisposable coveralls (soot and dust)GlovesSoft-soled, slip-resistant safety boots for roof workHarness and lanyard (where specified as a secondary control)

High Risk Construction Work Types

  • •Risk of a person falling more than 2 metres
  • •Demolition of an element of a structure that is load-bearing or related to its physical integrity
  • •Work that involves, or is likely to involve, disturbing asbestos
  • •Structural alterations or repairs that require temporary support to prevent collapse

Risk Assessment

1.Inspection and planning

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Unstable stack collapses during workHighInspect the stack from a safe position for cracking, lean and loose mortar. If unstable, get engineering advice and brace before anyone works next to it.ModerateSupervisor
Asbestos in flue pipes, flashings or backing boardsHighCheck the asbestos register or have suspect materials sampled. Licensed removalist removes asbestos before demolition.LowSupervisor

2.Roof access and fall protection

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Fall from roof edge or ladderCatastrophicPerimeter scaffold or roof edge protection installed before work. Access by scaffold stair or ladder secured top and bottom, extending 1 m above the landing. Licensed scaffolder where a fall of more than 4 m is possible.LowScaffolder / Supervisor
Fall through brittle roof sheets or broken tilesHighWorking platform around the stack built on the roof framing. No standing on fibre cement or skylight sheets. Crawl boards where needed.LowSupervisor

3.Protecting the interior and setting up debris control

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Debris falling down the flue into the houseHighSeal the fireplace opening from inside. Bag soot from the hearth. Do not drop bricks down the flue.LowLabourer
Falling debris strikes people belowCatastrophicEnclosed debris chute from platform into skip. Exclusion zone below the work area. Toe boards and catch screens on the scaffold.LowSupervisor

4.Top-down hand demolition of the stack

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Stack or large section topplingCatastrophicRemove one or two courses at a time with hand tools working from the top down. Never undercut or pull the stack. Stop in winds strong enough to destabilise the stack or blow dust and debris.ModerateDemolition Worker
Soot and brick dust inhalationHighLightly wet the work as you go. P2 respirator and coveralls. Wash hands and face before eating.LowDemolition Worker
Manual handling of bricks and capping stonesModerateBreak capping stones into manageable pieces or lower by hoist. Fill buckets to a weight one person can handle safely.LowDemolition Worker

5.Removing the internal chimney breast

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Collapse of remaining stack or framing after breast removalCatastrophicEngineer or competent person specifies temporary propping and permanent support. Props installed before any breast masonry is removed. Do not remove the breast while the stack above remains without confirmed support.LowEngineer / Supervisor
Dust spreading through the houseModeratePlastic sheeting to isolate the room. HEPA vacuum for clean-up.LowLabourer

6.Making good the roof and clean-up

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Water entry through open roof penetrationModerateTemporary weatherproof cover at the end of each day. Roof plumber or tiler makes good with flashing or matching cladding.LowSupervisor / Roofer
Lead exposure from old flashingsModerateWear gloves when handling lead. Wash hands before eating. Dispose of lead to a metal recycler.LowRoofer

Relevant Codes of Practice

Worker Acknowledgement

By signing below, I confirm that I have read, understood and agree to comply with this Safe Work Method Statement.

Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________