Important: This SWMS template is provided as a starting point only. It must be reviewed and customised to reflect the specific conditions, hazards, and controls for your workplace and task. The PCBU remains responsible for ensuring the SWMS is suitable for the specific work. This template does not constitute legal advice. Refer to your state or territory WHS regulator for compliance requirements.
Crane, Lifting & Rigging

Mobile Crane Operations — Safe Work Method Statement

Safe Work Method Statement for mobile crane operations on construction sites, including pre-lift planning, set-up, lifting operations and pack-up. Applies to all mobile cranes requiring a crane operator licence.

Download this template

Mobile crane operations are HRCW under Schedule 3 of the model WHS Regulations, specifically because they involve the use of a crane or hoist. A SWMS is mandatory before any mobile crane lift commences on a construction site. For complex or critical lifts — typically defined as lifts exceeding 90% of rated capacity, tandem lifts, or lifts over live services or occupied areas — a formal lift study prepared by a competent engineer is also required in addition to the SWMS.

Licensing requirements are strict and nationally consistent across all jurisdictions that have adopted the model WHS laws. A mobile crane operator must hold a high-risk work (HRW) licence in the relevant crane class — C2 for mobile cranes up to and including 60 tonne capacity, or C6 for any capacity. Dogman and rigging licences are required for other workers involved in attaching loads and directing the crane. All HRW licences are issued by the state or territory WHS regulator following nationally recognised training and assessment.

The mobile crane must be registered plant under the WHS Regulations if it exceeds the registration threshold. Pre-use inspection must be completed to the requirements of AS 2550.1 (Cranes, hoists and winches — Safe use — General requirements) and the manufacturer's maintenance schedule. Ground bearing capacity is a critical pre-lift engineering requirement — outrigger pad loads for large mobile cranes can exceed 200 tonnes per pad, and inadequate ground assessment has been responsible for a number of crane collapses in Australia. A geotechnical assessment or engineer's approval for outrigger placement is standard practice on complex sites.

To customise this template, document the crane make, model, and configuration; the load to be lifted (weight, dimensions, and centre of gravity); the lift radius and boom angle; the ground condition assessment; the exclusion zone dimensions; and the names and licence numbers of the crane operator, rigger, and dogman. The lift plan, load chart, and outrigger pad calculations should be attached as appendices.

This SWMS applies in all Australian jurisdictions. Western Australia adopted the model WHS laws in 2022. Victorian users must additionally comply with OHS Regulations 2017 and the Equipment (Public Safety) Act 1994.

Personal Protective Equipment

Hard HatHigh Visibility VestSafety Boots (Steel Capped)Safety GlassesGloves

High Risk Construction Work Types

  • Area in which there is any movement of powered mobile plant
  • Risk of a person falling more than 2 metres
  • On, in or adjacent to a road or traffic corridor in use by traffic other than pedestrians

Risk Assessment

1.Pre-lift planning and risk assessment

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Lift exceeds crane capacity at required radiusCatastrophicLift study completed by rigger/dogging licence holder using manufacturer load chart. Confirm total load weight (load + rigging). Confirm radius and boom configuration. Lift plan signed off before commencement.LowRigger / Crane Operator
Overhead powerlines within crane swing radiusCatastrophicIdentify all overhead powerlines within operating radius. Maintain minimum exclusion distances per relevant state regulation (typically 3 m for <33 kV). Apply to network operator for powerline undergrounding, guarding or isolation if required.LowSite Supervisor / Crane Operator

2.Crane set-up and outrigger deployment

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Crane overturning due to inadequate ground bearingCatastrophicGround bearing assessment completed before set-up. Outrigger pads sized to distribute load within bearing capacity. Level crane on firm, stable ground. Check for underground voids, services or soft fill.LowCrane Operator
Pinch point injury during outrigger extensionHighExclusion zone during outrigger deployment. Operator to confirm area is clear before extending outriggers. Use spotters.LowCrane Operator / Spotter

3.Rigging and slinging of load

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Rigging failure causing load dropCatastrophicRigging gear inspected before use (no damage, current tags). SWL of rigging exceeds load weight with appropriate safety factor. Slings at correct angles. Dogging performed by licenced dogman.LowLicenced Rigger / Dogman
Load shifting or swinging during liftHighTag lines attached to load before lift. Licenced dogman to guide load with tag lines. Load to be balanced before lifting. No free-swinging loads.LowLicenced Dogman

4.Lifting and placing load

Hazard / RiskInitial RiskControl MeasuresResidual RiskResponsibility
Personnel struck by suspended loadCatastrophicExclusion zone established under and around load path. No personnel to stand under suspended load. Lift to be suspended if exclusion zone is breached. Communication protocol agreed between operator and dogman.LowCrane Operator / Dogman / Site Supervisor
Loss of communication causing incorrect crane movementHighStandard hand signals or two-way radio used consistently. Crane operator to stop if communication is lost. One designated dogman/signaller only. Emergency stop signal known by all.LowCrane Operator / Dogman

Relevant Codes of Practice

Worker Acknowledgement

By signing below, I confirm that I have read, understood and agree to comply with this Safe Work Method Statement.

Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________
Name: ___________________Date: ___________________
Signature: ___________________________

Download this template

Go paperless with WorkSignals

Manage SWMS digitally — track sign-offs, attach photos, and access everything from your phone.

Try WorkSignals free